Port Talbot electric arc furnace

by Tata Steel UKGB

Restart steelmaking at the UK's largest steelworks with about 90% lower direct CO2, using domestic scrap and £500M of public money.

ProtoStage 2 of 5

Under construction since July 2025; start-up slipped to late 2028 or early 2029 on grid delays.

Updated 19d agoChecked 11 Oct0 updates this week

Milestones

Next · Furnace commissioning
  1. Grid connection agreement with National Grid ESOMay 2024Complete.
  2. £500M UK grant funding agreement signed11 Sep 2024Complete.
  3. Last blast furnace (No. 4) shut down30 Sep 2024Complete.
  4. Planning approval from Neath Port Talbot councilFeb 2025Complete.
  5. Construction starts14 Jul 2025Complete.
  6. Furnace commissioningTarget Q4 2028+12 mooriginally Q4 2027Current milestone.