Milestones
- Grid connection agreement with National Grid ESOMay 2024Complete.
- £500M UK grant funding agreement signed11 Sep 2024Complete.
- Last blast furnace (No. 4) shut down30 Sep 2024Complete.
- Planning approval from Neath Port Talbot councilFeb 2025Complete.
- Construction starts14 Jul 2025Complete.
- Furnace commissioningTarget Q4 2028+12 mo
originally Q4 2027Current milestone.
Most important updates
- Grid delays push Port Talbot furnace start to late 2028 or early 2029; Tata seeks more UK funding19d ago
- Construction begins on Tata Steel's £1.25B electric arc furnace at Port Talbot14 Jul 2025
- Port Talbot's last blast furnace shuts, ending ironmaking at the site30 Sep 2024
- Tata Steel signs £500M grant agreement with UK government for Port Talbot electric arc furnace11 Sep 2024
Upcoming
- Q4 2028Furnace commissioning+12 mo
originally Q4 2027(next)