Pilgangoora lithium operation

by PLS (formerly Pilbara Minerals)AU

Grow from about 1 Mt to about 2 Mt of concentrate a year at low cost, so the mine stays profitable through lithium price cycles while supplying battery demand.

ScalingStage 5 of 5

Ngungaju plant restarted July 2026; FY27 output guided at 1.03-1.10 Mt; P2000 feasibility study due Q4 2026.

Updated 30 Jul 2026Checked 11 Oct0 updates this week

Milestones

Next · P2000 feasibility study results
  1. P1000 expansion approved (A$560M)29 Mar 2023Complete.
  2. P680 expansion completed2 Aug 2024Complete.
  3. Ngungaju plant put on care and maintenanceDec 2024Complete.
  4. P1000 expansion first ore31 Jan 2025Complete.
  5. Ngungaju plant restartedJul 2026Complete.
  6. P2000 feasibility study resultsTarget Q4 2026+12 mooriginally Q4 2025Current milestone.