- Mine closes after waste spill and Chinese competition2002Complete.
- MP Materials' owners buy the mine out of bankruptcyJul 2017Complete.
- Mining and concentrate production resumeJan 2018Complete.
- DoD deal: $110/kg NdPr floor, $400M equity, $150M loanJul 2025Complete.
- All product sales to China stopJul 2025Complete.
- Price-floor payments startOct 2025Complete.
- Dy/Tb separation circuit commissioningTarget 2026Current milestone.
- First dysprosium and terbium shipped to Fort WorthTarget Q4 2026Not yet reached.
- New pre-flotation process at full scaleTarget 2028Not yet reached.
Most important updates
- Mountain Pass NdPr output up 41% to 840 t; MP commissioning its dysprosium-terbium circuit6 Aug 2026
- MP Materials posts record NdPr output, ends sales to China and sets mid-2026 start for heavy rare-earth separation6 Nov 2025
- MP Materials and the US Defense Department agree a $110/kg NdPr price floor, $400M equity and heavy rare-earth loan10 Jul 2025
Upcoming
- 2026Dy/Tb separation circuit commissioning (next)
- Q4 2026First dysprosium and terbium shipped to Fort Worth
- Nov 2026Q3 2026 NdPr production expected above 1,000 t
- 2028New pre-flotation process at full scale