Milestones
- RapidSX demonstration plant starts in Kingston, OntarioDec 2023Complete.
- Department of War adds US$18.4M for first commercial machineJul 2025Complete.
- MoU to supply NdPr and Dy oxide to Vulcan ElementsMar 2026Complete.
- Engineering report: Machine A plus three ~3,000 t/yr linesMay 2026Complete.
- Contactor scale-up up to 24-inch verifiedAug 2026Complete.
- Machine A installed and commissioned (600 t/yr)Target 2027+15 mo
originally Q4 2025Current milestone. - Commercial supply to Vulcan ElementsTarget 2027Not yet reached.
- Production Line 1 (~3,000 t/yr)Not yet reached.
Most important updates
- Ucore verifies RapidSX contactor scale-up to 24 inches for Louisiana5 Aug 2026
- Ucore engineering report resets Louisiana plan: 600 t/yr Machine A, three lines, ~9,600 t/yr target28 May 2026
- Ucore and Vulcan Elements sign MoU for Louisiana rare-earth oxides to feed US magnet plants24 Mar 2026
- Ucore readies Louisiana heavy rare-earth processing under its US Department of War agreement11 Dec 2025
Upcoming
- 2027Machine A installed and commissioned (600 t/yr)+15 mo
originally Q4 2025(next) - 2027Commercial supply to Vulcan Elements
- 1 Jan 2027New US sourcing restrictions on rare-earth materials take effect