Great Salt Lake Phase 1 DLE Plant

by Lilac SolutionsUS

A 5,000 tonne per annum lithium carbonate facility using direct lithium extraction on the Great Salt Lake in Utah. Gen 5 ion exchange technology extracts lithium directly from brine without large evaporation ponds.

PilotStage 3 of 5

FID targeted for late 2026; construction and first production 2027.

Updated Aug 2026Checked 10 Oct0 updates this week

Milestones

Next · Final investment decision
  1. Pilot operations completed, 87% recovery demonstrated2025Complete.
  2. Hatch selected as EPCM partnerJun 2026Complete.
  3. JordProxa selected for downstream conversionJul 2026Complete.
  4. Final investment decisionTarget 2026Current milestone.
  5. Construction beginsTarget 2026Not yet reached.
  6. First lithium productionTarget 2027Not yet reached.
Primer