Milestones
- California Energy Commission issues final permit19 Dec 2025Complete.
- Kern County Board franchise agreement approvalDec 2025Complete.
- Conditional letter of support from Kern County BoardApr 2025Complete.
- Construction beginsTarget 2026Current milestone.
- Facility comes onlineTarget 2030Not yet reached.
Most important updates
Upcoming
- 2026Construction begins (next)
- 2026Construction breakground at Willow Rock
- 2030Facility comes online
- 2030Facility begins operations