Willow Rock A-CAES

by HydrostorCA

500 MW / 4 GWh A-CAES facility in Kern County, California. Uses underground air caverns and thermal storage, with no fossil fuels during discharge.

PilotStage 3 of 5

Permit obtained December 2025; construction begins mid-2026; online 2030.

Updated Feb 2026Checked 10 Oct0 updates this week

Milestones

Next · Construction begins
  1. California Energy Commission issues final permit19 Dec 2025Complete.
  2. Kern County Board franchise agreement approvalDec 2025Complete.
  3. Conditional letter of support from Kern County BoardApr 2025Complete.
  4. Construction beginsTarget 2026Current milestone.
  5. Facility comes onlineTarget 2030Not yet reached.

Most important updates

Upcoming

  1. 2026Construction begins (next)
  2. 2026Construction breakground at Willow Rock
  3. 2030Facility comes online
  4. 2030Facility begins operations
Primer