Milestones
- V236-15.0 MW design completion2024Complete.
- First V236-15.0 MW turbine installed at He Dreiht (Germany)Apr 2025Complete.
- 100 V236-15.0 MW turbines installed (Baltic Power milestone)Jun 2026Complete.
- 200th V236 turbine installed at Hollandse Kust West VI18 Sep 2026Complete.
- He Dreiht (Germany) fully installed and operationalAug 2026Complete.
- Hollandse Kust West VI first power deliveryJul 2026Complete.
- Hollandse Kust West VI full commissioningTarget Q4 2026Current milestone.
Most important updates
- Vestas installs 200th V236-15.0 MW offshore turbine; cumulative capacity reaches 3 GWSep 2026
- Vestas completes turbine installation at He Dreiht offshore wind farm in Germany with 64 V236-15.0 MW turbinesAug 2026
- Hollandse Kust West VI offshore wind farm (Netherlands) begins delivering power with 52 V236-15.0 MW turbinesJul 2026
- Vestas reaches 100th V236-15.0 MW offshore turbine installation milestone at Baltic Power, PolandJun 2026
- Vestas installs first V236-15.0 MW offshore wind turbine at He Dreiht, GermanyApr 2025
Upcoming
- Q4 2026Hollandse Kust West VI full commissioning (next)
- Oct 2026Baltic Power (Poland) 76-turbine project completed installation
- 2027Future large offshore projects across Northern Europe