Project Pele

by BWX TechnologiesUS

Demonstrate a mobile microreactor capable of providing resilient power to forward military bases for three years without refueling.

ProtoStage 2 of 5

TRISO fuel core delivered to INL. Site construction underway. Testing scheduled 2027.

Updated 5 Nov 2025Checked 11 Oct0 updates this week

Milestones

Next · Reactor transport to INL
  1. Project Pele contract awarded2022Complete.
  2. TRISO fuel fabrication beginsDec 2022Complete.
  3. Full TRISO fuel core delivered to INLNov 2025Complete.
  4. Site construction begins at INLSep 2024Complete.
  5. Reactor transport to INLTarget 2026Current milestone.
  6. System testing beginsTarget 2027Not yet reached.