Milestones
- Oak Ridge, Tennessee named as the preferred siteSep 2024Complete.
- DOE selects Orano for up to $900M in support5 Jan 2026Complete.
- Environmental report filed with the NRCJan 2026Complete.
- Licence application completed (technical part)27 Mar 2026Complete.
- NRC accepts the application for an accelerated review21 May 2026Complete.
- NRC licensing decisionTarget Apr 2027Current milestone.
- LEU production beginsTarget 2031Not yet reached.
Most important updates
Upcoming
- Apr 2027NRC licensing decisionin about 25 weeks (next)
- 1 Jan 2028US waivers for Russian enriched uranium end
- 2031LEU production begins