Milestones
- IAEA design safety review approval2016Complete.
- First concrete poured at Changjiang siteJul 2021Complete.
- Cold functional testing completed16 Oct 2025Complete.
- Non-nuclear steam test completed23 Dec 2025Complete.
- Hot functional testing beginsTarget Oct 2026Current milestone.
- Fuel loading and criticalityTarget 2027Not yet reached.
- Grid connection and commercial operationTarget 2027Not yet reached.
Most important updates
Upcoming
- Oct 2026Hot functional testing begins (next)
- 2027Fuel loading and criticality
- 2027Grid connection and commercial operation