Milestones
- Licence to construct from Canada's nuclear regulatorApr 2025Complete.
- Ontario's final investment decision; unit 1 construction starts8 May 2025Complete.
- Federal and Ontario funds take a 22.5% stake for C$3B23 Oct 2025Complete.
- Operating licence application filed for unit 1Mar 2026Complete.
- Unit 1 basemat set in the 35 m reactor shaft22 Apr 2026Complete.
- Williams Treaties First Nations invest C$700M23 Jun 2026Complete.
- First reactor building level complete (200+ modules)Target Q4 2026Current milestone.
- Approval to proceed with units 2-4Target 2028Not yet reached.
- Unit 1 connected to the gridTarget Q4 2030Not yet reached.
- Units 2-4 in serviceNot yet reached.
Most important updates
- Williams Treaties First Nations invest C$700 million in OPG's Darlington SMR project23 Jun 2026
- Canada Growth Fund and Building Ontario Fund commit C$3 billion for 22.5% of the Darlington SMR project23 Oct 2025
- Ontario approves construction of the first of four BWRX-300 small reactors at Darlington8 May 2025
Upcoming
- Q4 2026First reactor building level complete (200+ modules) (next)
- 2028Approval to proceed with units 2-4
- Q4 2030Unit 1 connected to the grid