Darlington New Nuclear Project

by Ontario Power GenerationCA

Prove that small reactors can be built on budget in a Western country, then repeat the design so each unit gets cheaper: from C$6.1 billion for the first to about C$4.1 billion for the fourth.

PilotStage 3 of 5

Unit 1 basemat set April 2026; grid target end-2030; go-ahead for units 2-4 expected 2028.

Updated 23 Jun 2026Checked 11 Oct0 updates this week

Milestones

Next · First reactor building level complete (200+ modules)
  1. Licence to construct from Canada's nuclear regulatorApr 2025Complete.
  2. Ontario's final investment decision; unit 1 construction starts8 May 2025Complete.
  3. Federal and Ontario funds take a 22.5% stake for C$3B23 Oct 2025Complete.
  4. Operating licence application filed for unit 1Mar 2026Complete.
  5. Unit 1 basemat set in the 35 m reactor shaft22 Apr 2026Complete.
  6. Williams Treaties First Nations invest C$700M23 Jun 2026Complete.
  7. First reactor building level complete (200+ modules)Target Q4 2026Current milestone.
  8. Approval to proceed with units 2-4Target 2028Not yet reached.
  9. Unit 1 connected to the gridTarget Q4 2030Not yet reached.
  10. Units 2-4 in serviceNot yet reached.

Most important updates

Upcoming

  1. Q4 2026First reactor building level complete (200+ modules) (next)
  2. 2028Approval to proceed with units 2-4
  3. Q4 2030Unit 1 connected to the grid