Constellation is restarting Three Mile Island Unit 1, a 835 MW pressurized water reactor shut down in 1999, to supply power to Microsoft data centers under a 20-year power purchase agreement.

DeployStage 4 of 5

NRC fuel license amendment approved. Restart targeted for 2027, pending transmission upgrades.

Checked 10 Oct0 updates this week

Milestones

Next · Reactor restart and grid connection
  1. Three Mile Island Unit 1 shut down1999Complete.
  2. NRC fuel license amendment approvedQ3 2026Complete.
  3. Reactor restart and grid connectionTarget 2027Not yet reached.
  4. Full commercial operationTarget Q4 2027Not yet reached.

Upcoming

  1. 2027Reactor restart and grid connection (next)
  2. Q4 2027Full commercial operation