Give India its own large AI computing base so Indian firms and Jio's users need not rent intelligence from abroad, and cut the cost of AI the way Jio cut the cost of mobile data.

PilotStage 3 of 5

Under construction; first 120 MW on NVIDIA GB300 due by end of 2026, Meta's 168 MW within two years.

Updated 19 Jun 2026Checked 11 Oct0 updates this week

Milestones

Next · First 120 MW of AI compute commissioned
  1. NVIDIA partnership for gigawatt AI site at Jamnagar24 Oct 2024Complete.
  2. Reliance Intelligence unit formed; Google Cloud deal for Jamnagar29 Aug 2025Complete.
  3. Rs 10 lakh crore, seven-year AI plan announced19 Feb 2026Complete.
  4. Meta signs for a 168 MW build-to-suit hall10 Jun 2026Complete.
  5. First 120 MW of AI compute commissionedTarget Q4 2026Current milestone.
  6. Meta's 168 MW hall deliveredTarget 2028Not yet reached.