Give US open science more than ten times the computing of today's Perlmutter machine for simulation and AI, and analyse data streamed live from telescopes, fusion machines and sequencers.

PilotStage 3 of 5

Test system Cech delivered Jan 2026; full Doudna system due to be installed late 2026.

Updated 17 Mar 2026Checked 11 Oct0 updates this week

Milestones

Next · Full Doudna system deployed
  1. DOE picks Dell and NVIDIA; system named Doudna29 May 2025Complete.
  2. Early-access system Cech deliveredJan 2026Complete.
  3. Full Doudna system deployedTarget Q4 2026Current milestone.
  4. Doudna open to NERSC usersNot yet reached.