Dholera Fab

by Tata ElectronicsIN

Establish India's domestic semiconductor manufacturing capability and supply chain.

ProtoStage 2 of 5

Under construction; commercial production targeted for mid-2028, starting at 90nm and 55nm nodes.

Updated Jul 2026Checked 11 Oct0 updates this week

Milestones

Next · Fab construction and equipment installation
  1. Land acquisition and construction begins2023Complete.
  2. Fab construction and equipment installationTarget 2026Current milestone.
  3. Pilot production at 90nm and 55nmTarget Apr 2028Not yet reached.
  4. Commercial production rampTarget Jul 2028Not yet reached.
  5. 28nm technology node introductionTarget 2030Not yet reached.

Most important updates

Upcoming

  1. 2026Fab construction and equipment installation (next)
  2. Apr 2028Pilot production at 90nm and 55nm
  3. Jul 2028Commercial production ramp
  4. 203028nm technology node introduction