Milestones
- Groundbreaking in Covington, Georgia1 Nov 2022Complete.
- CHIPS Act terms: up to $75M23 May 2024Complete.
- Evaluation samples to global customersApr 2026Complete.
- Embedded samples enter reliability evaluationJul 2026Complete.
- Pass customer reliability testsTarget 2026Current milestone.
- Full-scale productionTarget 2027+36 mo
originally 2024Not yet reached.
Most important updates
- Absolics launches a ₩401.1B rights issue to fund customer qualification and yield20 Aug 2026
- SKC targets full-scale glass substrate production in 2027 after customer requirements change24 Jul 2026
- Glass substrates still short of mass production as Absolics' timeline slips again14 Jun 2026
- Absolics agrees terms for up to $75M in CHIPS Act funding for its Georgia glass substrate plant23 May 2024
Upcoming
- 2026Pass customer reliability tests (next)
- 2027Full-scale production+36 mo
originally 2024