Covington glass substrate plant

by AbsolicsUS

Replace the resin boards under AI chip packages with glass, which stays flat as packages grow and carries denser, lower-loss wiring, so bigger multi-chip AI processors can be built reliably.

PilotStage 3 of 5

Plant built; samples in customer reliability testing, volume production now expected in 2027.

Updated 20 Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · Pass customer reliability tests
  1. Groundbreaking in Covington, Georgia1 Nov 2022Complete.
  2. CHIPS Act terms: up to $75M23 May 2024Complete.
  3. Evaluation samples to global customersApr 2026Complete.
  4. Embedded samples enter reliability evaluationJul 2026Complete.
  5. Pass customer reliability testsTarget 2026Current milestone.
  6. Full-scale productionTarget 2027+36 mooriginally 2024Not yet reached.
Primer