Next-Gen OPIR

by US Space ForceUS

Replace the ageing SBIRS satellites with ones that can see dimmer, faster missiles, including hypersonic weapons, and are harder for an adversary to blind or attack.

PilotStage 3 of 5

First GEO satellite built, waiting on Vulcan, grounded for military flights since Feb 2026. Polar sats: 2028.

Updated 26 Mar 2026Checked 11 Oct0 updates this week

Milestones

Next · First GEO satellite (NGG-1) launch on Vulcan
  1. Lockheed Martin GEO contract ($2.9B)2018Complete.
  2. GEO system-level critical design review complete28 Oct 2021Complete.
  3. First GEO infrared payload delivered by RTX, 13 months lateAug 2024Complete.
  4. First GEO satellite (NGG-1) launch on VulcanNowCurrent milestone.
  5. First polar satellite launch (Northrop Grumman)Target 2028Not yet reached.

Most important updates

Upcoming

  1. 2028First polar satellite launch (Northrop Grumman) (next)
Primer