Milestones
- Project initiated2015Complete.
- Permitting and environmental review begin2016Complete.
- U.S. District Court rules in favor of Thacker Pass permittingFeb 2023Complete.
- Detailed engineering design 95% completeQ1 2026Complete.
- Construction in full swing, 1,600+ workers on-siteQ2 2026Complete.
- Mechanical completionTarget Q4 2027Current milestone.
- Commercial production rampTarget Q1 2028Not yet reached.
Most important updates
Upcoming
- Q4 2027Mechanical completion (next)
- Q1 2028Commercial production ramp