Kendal anode materials plant

by BTR New Material GroupCN

Supply high-quality anode materials to battery makers in Asia and globally, supporting millions of EV batteries per year.

DeployStage 4 of 5

Phase 1 (80 kt/yr) opened August 2024. Phase 2 (80 kt/yr) completing late 2025.

Updated Q1 2025Checked 11 Oct0 updates this week

Milestones

Next · Phase 2 construction targets completion
  1. Phase 1 plant inaugurated by Indonesian President WidodoAug 2024Complete.
  2. Phase 1 production commencesQ3 2024Complete.
  3. Phase 2 construction targets completionTarget Q4 2025Current milestone.
  4. Phase 2 production ramp-upTarget Q2 2025Not yet reached.
  5. Full capacity 160 kt/yr achievedTarget Q3 2025Not yet reached.

Most important updates

Upcoming

  1. Q2 2025Phase 2 production ramp-up (next)
  2. Q3 2025Full capacity 160 kt/yr achieved
  3. Q4 2025Phase 2 construction targets completion