HyREX hydrogen direct reduction

by POSCOKR

Prove hydrogen-based steelmaking works at 300 kt/yr scale, validate ore supply chains, and establish economics for commercial 1–2 Mt/yr plants by early 2030s.

PilotStage 3 of 5

Demo plant under construction in Pohang. First trial operation due 2028.

Updated 30 Oct 2025Checked 11 Oct0 updates this week

Milestones

Next · Demo plant first trial operation
  1. HyREX process development2010Complete.
  2. Pilot plant at Pohang research centre2017Complete.
  3. Decision for 300 kt/yr demo plant2021Complete.
  4. BHP partnership agreement30 Oct 2025Complete.
  5. Demo plant first trial operationTarget 2028Not yet reached.
  6. Commercial-scale deployment decisionTarget 2029Not yet reached.

Most important updates

Upcoming

  1. 2028Demo plant first trial operation (next)
  2. 2029Commercial-scale deployment decision