Duisburg DRI Plant (tkH2Steel)

by ThyssenKrupp SteelDE

Replace blast furnaces at Germany's largest steelworks with a plant that can switch from gas to hydrogen. It is one of the biggest single cuts in industrial CO2 in Europe.

PilotStage 3 of 5

Being built; starts on natural gas. Hydrogen tender on hold; EU eased the hydrogen funding rule in Aug 2026.

Updated Aug 2026Checked 11 Oct0 updates this week

Milestones

Next · Plant commissioning with natural gas reducing agent
  1. SMS Group awarded €1.8B contract for plant design and constructionMar 2023Complete.
  2. EU approves €2 billion in co-funding for the projectJul 2023Complete.
  3. Hydrogen supply tender put on hold over high pricesMar 2025Complete.
  4. EU approves funding change so it can start without hydrogenAug 2026Complete.
  5. Plant commissioning with natural gas reducing agentTarget Q4 2026Current milestone.
  6. Transition to hydrogen as primary reducing agentNot yet reached.
  7. Full production at 2.5 million tonnes DRI per yearTarget 2028Not yet reached.

Most important updates

Upcoming

  1. Q4 2026Plant commissioning with natural gas reducing agent (next)
  2. 2028Full production at 2.5 million tonnes DRI per year