Centenario-Ratones DLE plant

by ErametFR

Establish reliable, cost-competitive lithium supply through direct extraction from brines, avoiding large solar ponds and reducing water use.

DeployStage 4 of 5

90% capacity in June 2026. Extension to 35 kt-LCE approved for study; FID Q4 2027.

Updated Q3 2026Checked 11 Oct0 updates this week

Milestones

Next · Target full capacity and positive EBITDA
  1. Commissioning beginsJul 2024Complete.
  2. First lithium carbonate productionDec 2024Complete.
  3. Commercial ramp-upQ1 2025Complete.
  4. 90% nameplate capacity reachedJun 2026Complete.
  5. Target full capacity and positive EBITDATarget Q4 2026Current milestone.
  6. Phase 1 extension FID decisionTarget Q4 2027Not yet reached.

Most important updates

Upcoming

  1. Q4 2026Target full capacity and positive EBITDA (next)
  2. Q4 2026Centenario-Ratones reaches 100% capacity
  3. Q4 2027Phase 1 extension FID decision