Milestones
- Hanwha acquires Philadelphia Shipyard2024Complete.
- $5 billion modernization plan announcedAug 2025Complete.
- Two additional docks under constructionTarget 2026Current milestone.
- First MRIV deliveryTarget 2030Not yet reached.
- Ramp to 20 ships/year capacityTarget 2029Not yet reached.
Most important updates
Upcoming
- 2026Two additional docks under construction (next)
- 2027Austal USA acquisition closing (if approved)
- 2027First new dock operational
- 2029Ramp to 20 ships/year capacity
- 2030First MRIV delivery