Milestones
- USDA-ACOE announce sterile fly facility projectMar 2026Complete.
- Groundbreaking ceremony at Moore Air Base17 Apr 2026Complete.
- Facility opening and production beginsTarget Q2 2027Not yet reached.
- Phase 1 capacity reached: 100 million flies per weekTarget Nov 2027Not yet reached.
- Phase 2 capacity reached: 300 million flies per weekTarget Dec 2028Not yet reached.
Most important updates
Upcoming
- Q2 2027Facility opening and production begins (next)
- Nov 2027Phase 1 capacity reached: 100 million flies per week
- Dec 2028Phase 2 capacity reached: 300 million flies per week